14 July 2000 - 3,000 tonnes of stone is placed in the river, test bore holes drilled. |
 |
22 July 2000 - Foundations for steel support, ground preparation. |
 |
31 July 2000 - Piling operation/preparations for steel work |
| August 2000 |
 |
12-14 August 2000 - Piling operations/foundations almost complete |
 |
15-17 August 2000 - 300 tonne crane and support steel arrive and are manoeuvred into place |
 |
23-31 August 2000 - The support structure in place, surveys of the bridge commence - preparation for piling into central pier |
| September 2000 |
 |
09-17 September 2000 - Piling operation begins from the top of the bridge |
 |
22-31 September 2000 - Piling operation starts at the foot of the central pier - work area flooded |
| October 2000 |
 |
01 October 2000 - Piling operation complete - preparation for temporary bridge |
 |
05-10 October 2000 - Opening of the bridge to light traffic - central pier damaged foundations revealed |
 |
15 Oct-03 Nov 2000 - Cofferdam in place - new stone arrives. 27/10 Visit by William Hague MP - 03/11 Flooding slows work |
| November 2000 |
 |
10-22 Nov 2000 - Stonework starts on the central pier. Costs go up to £2m |
 |
24-30 Nov 2000 - The central pier complete - work on the arches commences. |
| December 2000 |
 |
03-07 Dec 2000 - Stonework on the arches makes progress. |
 |
08 - 17 Dec 2000 - Stonework on the arches almost complete. Concrete infilling starts. Bat roosts made. Preparation for opening. |
 |
21 Dec 2000 - Bridge open fully to traffic. |
| January 2001 |
 |
Jan 2001 - A closer look at the new stone. |
| April 2001 |
 |
April-May 2001 - The reinstatement of the site begins. |
| June 2001 |
 |
June 2001 - One year later - anti-scouring measures and flood channels created with new footpaths. |
| July 2001 |
 |
July 2001 - South side reinstatement work completed. |