Excavation in Bay 4.
The excavation in Bay 4 was stopped because bedrock was not found. The trench was over 5 metres deep, which was greater than the depth of the bedrock, found in Bay 2. The bottom of the trench was also below the level of the rock in the River Swale.
Reinforcement is placed in the bottom of the excavation to strengthen the concrete. Stainless steel dowel bars are also fixed to the stone retaining wall.
Concrete is poured into Bay 4 in stages between 11th and 13th June.
On each of the three days 30m3 of concrete is poured. Each Readmix lorry carries a load of 6m3.
|
|
 |
 |
 |
 |
|