01/10 - Left and below

The piling operation is now complete, and preparations are being made to put the temporary bridge over the damaged central pier.

The bridge should then be ready for light vehicles and pedestrians - before the end of this week.

The bridge - looking into Richmond.

The temporary bridge will be placed on this section.

The temporary bridge ready for installation on Station bridge.

 

03/10

The river is being diverted away from the base of the central pier so work can start rebuilding the foundations on the piles that have been drilled.

This work could be hampered if the river level rises too high.